I-75 widening and reconstruction

Add Through Lane(s)

Project Status

  1. Proposed

  2. In Development

  3. Pre-construction

  4. Construction

  5. Completion

About the project

BEGIN: March 2017

COMPLETE: Fall 2020

COST: $114 million

CONTRACTOR: Beaver Excavating Inc.

 

Interstate 75 from the area south of Harrison Street/county Road 144, which is just south of the U.S. 68/state Route 15 interchange, to the county Road 99 interchange within the city of Findlay is under construction during a $114 million reconstruction and widening project. The project will improve the safety and efficiency of the corridor and increase its capacity.

The project will add one travel lane in both the northbound and southbound direction along I-75 within the project area.

The interchanges at U.S. 68/state Route 15 and Lima Avenue will also be reconstructed as part of the project.

Beaver Construction, Canton, serves as the general contractor for the project. The anticipated completion is late 2020.

 

Work to continue in 2020 to complete the project:

The greatest concentration of work is now occurring at the interchange at U.S. 68/state Route 15 with I-75. 

  • Construction on the following ramps at the interchange will continue until late fall. Traffic will continue to be detoured north on I-75 to the state Route 12 interchange and back on I-75 southbound until the ramps are opened:
    • I-75 northbound to U.S. 68/state Route 15
    • I-75 northbound to Lima Avenue
    • U.S. 68/state Route 15 to I-75 southbound
    • Lima Avenue to I-75 southbound
  • Work at the Lima Avenue interchange will continue with grading and seeding, and installation of lighting, pedestrian beacons, signage, and landscaping. Little impact to traffic is expected.
  • The majority of work on I-75 itself is occurring between Harrison Street to the U.S. 68/state Route 15 interchange where the reconstruction and expansion of the northbound lanes continues. Two lanes of traffic are maintained the majority of time.
  • All four lanes of I-75 in this section are traveling on the southbound side and will remain in this pattern until late fall. This allows the northbound existing lanes to be reconstructed and a new, third lane to be constructed. A
  • All existing I-75 pavement has been removed and the intermediate pavement placed through this section.
  • Work to extend a noise wall on the west side of I-75 from Bigelow Avenue to the south will begin in June and is expected to complete in September. 
  • All lanes of I-75 will open late summer.

 

 

Current traffic impacts

  • Interstate 75 two lanes of traffic will be maintained through the work zone the majority of time. 
  • Traffic will continue to be detoured north on I-75 to the state Route 12 interchange and back on I-75 southbound until late fall.
  • Between Harrison Street to the U.S. 68/state Route 15 interchange all four lanes will continue to travel the southbound side until late summer.

NEW IMPACT

(Tuesday, March 31,2020) Interstate 75 northbound in Findlay will be restricted to one lane on Wednesday, Apr. 1, and Thursday, Apr. 2, for beam setting over the railroad. On both days, the restriction will begin at noon and continue until four beams are set.

The right lane of Interstate 75 northbound will close from the southern end of the project, just south of Harrison Street/county Road 144, to the Sandusky Street overpass, which is just south of the state Route 12 interchange.

Motorists should slow down, use extra caution and drive distraction-free through all work zones.  If possible, use an alternate route to avoid delays.

Live view of beam setting site is shown below.

 

Lima Avenue roundaboutLima Ave traffic

The Lima Avenue double roundabout at I-75 and U.S. 68/state Route 15 is now open. Select movements on the ramps to the north of the roundabout will be restricted through the end of the project as reconstruction activities continue at the interchange. Restricted movements are expected to open in late 2020.

When the interchange is finished, direct access will be available between I-75, U.S. 68/state Route 15, and Lima Avenue. View the navigation guide for all interchange movements.

For proven safety benefits and advantages of roundabouts, visit ODOT's roundabout web page.

 

 

OHGO: Live traffic info and cameras within work zone | link

756815

75224     7599

Cameras are updated every 15 seconds. Refresh your browser for the most current image.

View Project's Public Comments ()

Public comments regarding our projects are always welcome!

This section is for frequently asked questions and project-related questions. You may notice that some projects require one or more formal comment period(s) with deadlines for comments to be considered during certain phase(s) of the project development process. Typically called the “public comment period," this is when ODOT asks the public for input before an important decision needs to be made, such as choosing a preferred alternative. You may notice these periods generally occur immediately following a public meeting.

All comments received, regardless of when or how they are submitted, will be reviewed and considered and/or responded to by the ODOT project team. Comments received through this forum will, when appropriate, be publicly posted along with ODOT’s response; Such comments will be moderated to remove personal information prior to posting.

Please let us know if you have questions, and thank you for your interest and input on the project! 

Filter by Area of Interest

You can filter this list filtering with the topics on the list below.

Leave a Comment